The application for a waste tire facility permit consists of a general application that includes the appropriate supporting documents, map, and additional application information specific to the facility that is the subject of the application. The content requirements of the general permit application are set forth in part 9220.0270. The additional application information requirements specific to the facility type are set forth in parts 9220.0280 to 9220.0310, and must be submitted with the permit application.
Applicants for a waste tire facility permit shall submit a completed permit application to the commissioner, and a copy to the county where the facility is located or proposed to locate, and shall retain a copy for their records.
A person shall submit a permit application in accordance with items A and B.
For a waste tire processing or storage facility, a person shall submit a permit application at least 180 days before the planned date of facility construction for a new facility or for an existing facility no later than 90 days after May 23, 1988.
For a waste tire transfer facility, a person shall submit a permit application at least 90 days before the planned date of facility construction for a new facility or for an existing facility no later than 90 days after May 23, 1988.
A written application for renewal of an existing permit must be submitted 90 days before the expiration date of the existing permit.