The fee for processing an application shall be:
$20,000 for a nuclear waste storage or disposal facility; plus such additional fees as are reasonably necessary for completion of the evaluation of need for the proposed facility.
Fifty percent of the fee set according to subpart 1, items A to D shall accompany the application and the balance shall be paid 90 days after submission of the application. The applicant shall be notified prior to the time the application is acted upon by the commission of any additional fees, which fees shall be paid within 30 days of notification. The billing of such additional fees shall be accompanied by an itemized document showing the necessity for the additional assessment.
L 1983 c 289 s 115
November 14, 2003
Official Publication of the State of Minnesota