Part | Title |
---|---|
7854.0100 | DEFINITIONS. |
7854.0200 | PURPOSE. |
7854.0300 | PERMIT REQUIREMENT. |
7854.0400 | FILING APPLICATION FOR SITE PERMIT; PROTECTING DATA. |
7854.0500 | SITE PERMIT APPLICATION CONTENTS. |
7854.0600 | APPLICATION ACCEPTANCE. |
7854.0700 | PUBLIC ADVISOR. |
7854.0800 | PRELIMINARY DETERMINATION AND DRAFT SITE PERMIT. |
7854.0900 | PUBLIC PARTICIPATION. |
7854.1000 | FINAL SITE PERMIT DECISION. |
7854.1100 | PERMIT AUTHORITY LIMITED. |
7854.1200 | DELAY IN CONSTRUCTION. |
7854.1300 | SITE PERMIT AMENDMENT OR REVOCATION. |
7854.1400 | PERMIT TRANSFER. |
7854.1500 | FEES. |
"Associated facilities" means facilities, equipment, machinery, and other devices necessary to the operation and maintenance of a large wind energy conversion system, including access roads, collector and feeder lines, and substations.
"Construction" means to begin or cause to begin as part of a continuous program the placement, assembly, or installation of facilities or equipment or to conduct significant site preparation work for installation of facilities or equipment. Entering into binding power purchase contracts or obtaining wind easements from property owners or gathering wind data is not construction.
"Draft site permit" means a document prepared by the chair that indicates a preliminary decision to issue a site permit with particular terms and conditions.
"EQB Monitor" means the biweekly bulletin published by the Environmental Quality Board.
"Large wind energy conversion system" or "LWECS" means a combination of wind energy conversion systems with a combined nameplate capacity of 5,000 kilowatts or more.
"Person" means an individual, partnership, joint venture, private or public corporation, association, firm, public service company, cooperative, political subdivision, municipal corporation, government agency, public utility district, or any other entity, public or private, however organized.
"Power purchase agreement" means a legally enforceable agreement between two or more persons where one or more of the signatories agrees to provide electrical power and one or more of the signatories agrees to purchase the power.
"Site permit" means a document issued by the commission authorizing a person or persons to construct a large wind energy conversion system under the terms and conditions specified in the document.
"Small wind energy conversion system" or "SWECS" means a combination of wind energy conversion systems with a combined nameplate capacity of less than 5,000 kilowatts.
"Wind energy conversion system" or "WECS" means a device such as a wind charger, windmill, or wind turbine and associated facilities that converts wind energy to electric energy.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
This chapter provides for the consideration of applications for site permits for large wind energy conversion systems by the Minnesota Public Utilities Commission. This chapter is intended to provide for the siting of large wind energy conversion systems in an orderly manner compatible with environmental preservation, sustainable development, and the efficient use of resources.
26 SR 1394: L 2005 c 97 art 3 s 19
September 18, 2009
No person may construct an LWECS without a site permit from the commission. No person may commence construction of an LWECS until the commission has issued a site permit for the LWECS.
A site permit from the commission is not required to construct an SWECS. Nothing in this chapter precludes a local governmental unit from establishing requirements for the siting and construction of an SWECS.
No person may expand an existing LWECS by any amount or expand an SWECS to exceed 5,000 kilowatts without a site permit from the commission. A new project is considered an expansion of an existing WECS if the new WECS is within five miles of any turbine in the existing WECS, both projects are under common ownership, and a permit application for the new WECS is submitted to the PUC less than three years after the existing WECS commenced operation. Two WECS are under common ownership if the proposer of the new project, or a principal of the proposer, has an ownership or other financial interest in the existing WECS, although two projects are not under common ownership solely because the same person provided equity financing for both projects. The requirements of this subpart do not apply to any proposed SWECS for which the necessary local approvals were obtained prior to October 1, 2002, and for which construction started prior to December 31, 2002.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
A person seeking a site permit for an LWECS shall file three copies of the application for the site permit with the PUC for review prior to acceptance of the application.
A person filing an application for a site permit for an LWECS shall provide the PUC with an electronic version of the application suitable for posting on the PUC web page. An applicant may request that the commission waive this requirement, completely or in part, if an electronic version of the application is difficult or expensive for the applicant to obtain.
An applicant for a site permit for an LWECS may certify, according to the Minnesota Government Data Practices Act or other applicable law, that certain information in the application is trade secret information or other protected data or information that is not available to the public. The commission shall determine if the certified data or information satisfies the requirements for the protected classification and shall advise the applicant of the commission's determination before releasing any certified data or information. An applicant may withdraw its application if the commmission determines that the data or information is not entitled to the protected classification. Any person aggrieved by the decision of the commission regarding the status of certain data may request the commission to reconsider it's decision. The PUC shall ensure that data or information that is entitled to a protected classification is used and disclosed only according to applicable law.
26 SR 1394; L 2005 c 97 art 3 s 19
September 10, 2018
An applicant for a site permit must provide the following background information regarding the applicant:
the complete name, address, and telephone number of the applicant and any authorized representative;
the signature of the preparer of the application if prepared by an agent or consultant of the applicant;
the identity of any other LWECS located in Minnesota in which the applicant, or a principal of the applicant, has an ownership or other financial interest;
The applicant shall state in the application whether a certificate of need for the system is required from the commission and, if so, the anticipated schedule for obtaining the certificate of need. The commission shall not issue a site permit for an LWECS for which a certificate of need is required until the applicant obtains the certificate, although the commission may process the application while the certificate of need request is pending before the commission.
The commission may determine if a certificate of need is required for a particular LWECS for which the commission has received a site permit application.
If a certificate of need is not required from the commission, the applicant shall include with the application a discussion of what the applicant intends to do with the power that is generated. If the applicant has a power purchase agreement or some other enforceable mechanism for sale of the power to be generated by the LWECS, the applicant shall, upon the request of the commission, provide the commission with a copy of the document.
The applicant shall describe in the application how the proposed LWECS project furthers state policy to site such projects in an orderly manner compatible with environmental preservation, sustainable development, and the efficient use of resources.
The applicant shall include the following information about the site proposed for the LWECS and any associated facilities:
the boundaries of the site proposed for the LWECS, which must be delineated on a United States Geological Survey Map or other map as appropriate;
other meteorological conditions at the proposed site, including the temperature, rainfall, snowfall, and extreme weather conditions; and
The applicant shall include in the application information describing the applicant's wind rights within the boundaries of the proposed site.
The applicant shall provide the following information regarding the design of the proposed project:
a description of the turbines and towers and other equipment to be used in the project, including the name of the manufacturers of the equipment;
a description of the LWECS electrical system, including transformers at both low voltage and medium voltage; and
An applicant for a site permit shall include with the application an analysis of the potential impacts of the project, proposed mitigative measures, and any adverse environmental effects that cannot be avoided, in the following areas:
public health and safety, including air traffic, electromagnetic fields, and security and traffic;
rare and unique natural resources.
The analysis of the environmental impacts required by this subpart satisfies the environmental review requirements of chapter 4410, parts 7849.1000 to 7849.2100, and Minnesota Statutes, chapter 116D. No environmental assessment worksheet or environmental impact statement shall be required on a proposed LWECS project.
The applicant shall describe the manner in which the project, including associated facilities, will be constructed.
The applicant shall describe how the project will be operated and maintained after construction, including a maintenance schedule.
The applicant shall describe the estimated costs of design and construction of the project and the expected operating costs.
The applicant shall include an anticipated schedule for completion of the project, including the time periods for land acquisition, obtaining a site permit, obtaining financing, procuring equipment, and completing construction. The applicant shall identify the expected date of commercial operation.
The applicant shall identify the energy expected to be generated by the project.
The applicant shall include the following information regarding decommissioning of the project and restoring the site:
The applicant shall include in the application a list of all known federal, state, and local agencies or authorities, and titles of the permits they issue that are required for the proposed LWECS.
26 SR 1394; L 2005 c 97 art 3 s 19
October 13, 2009
Within 30 days after receipt of an application for a site permit, the commission shall accept, conditionally accept, or reject the application. If the commission conditionally accepts or rejects an application, the commission shall advise the applicant in writing of the deficiencies in the application and the manner in which the deficiencies can be addressed. Upon refiling of a revised application, the commission shall again act on the application within 30 days after receipt.
Within 15 days after commission acceptance of an application, the applicant shall provide notice of the application to the county board, each city council, and each township board in each county where the LWECS is proposed to be located and shall publish notice of the application in a newspaper of general circulation in each county. Failure to give this notice or a delay in providing this notice constitutes cause to reject an application or delay a decision by the commission. The commission may elect to give this notice in lieu of requiring the applicant to provide the notice.
Upon acceptance of the application by the commission, the commission shall advise the applicant of how many additional copies of the application to submit to the PUC. The applicant shall also provide a copy of the accepted application to the Minnesota Historical Society and to each landowner within the boundaries of the proposed LWECS site. The applicant shall also provide a copy to the office of each regional development commission of a development region, the auditor of each county, and the clerk of each city and township in which the LWECS is to be located. Each county auditor, city clerk, and township clerk shall retain the application and make it available for public inspection upon request. The applicant shall maintain a list of all persons to whom copies of the application are provided.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
Upon acceptance of an application for a site permit, the commission shall designate a staff person to act as the public advisor on the project. The public advisor shall be available to answer questions from the public about the permitting process. The public advisor shall not give legal advice or other advice that may affect the legal rights of the person being advised, and the public advisor shall not act as an advocate on behalf of any person.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
Within 45 days after acceptance of the application by the commission, the commission shall make a preliminary determination whether a permit may be issued or should be denied. If the preliminary determination is to issue a permit, the commission shall prepare a draft site permit for the project. The draft site permit must identify the person or persons who will be the permittee, describe the proposed LWECS, and include proposed permit conditions.
A draft site permit does not authorize a person to construct an LWECS. The commission may change the draft site permit in any respect before final issuance or may deny the site permit.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
Upon preparation of a draft site permit, the PUC shall provide public notice of the draft site permit. The public notice must include the following:
the location where a copy of the site permit application may be reviewed and how a copy of the application may be obtained;
the name of the public advisor and how the public advisor may be contacted to obtain more information;
a statement that during the comment period any person may submit comments to the commission on the draft site permit, a statement of the dates on which the comment period commences and terminates, and a statement that any person may request a contested case hearing on the matter; and
a brief description of the anticipated procedures for reaching a final decision on the permit application.
The PUC shall publish the notice in a newspaper in each county in which the proposed LWECS is to be located. The PUC shall also mail the public notice to those persons known to the PUC to be interested in the proposed LWECS project, including governmental officials in each county in which the LWECS is proposed to be located. The PUC shall also publish notice in the EQB Monitor.
The PUC shall afford the public a minimum of 30 days after publication of the draft site permit notice in the EQB Monitor to submit written comments to the PUC. The commission may extend the public comment period if necessary to afford the public adequate time to review the application and other pertinent information in order to formulate complete comments on the draft site permit and the project.
The PUC shall hold at least one public information meeting in a convenient location in the vicinity of the proposed LWECS project. The PUC shall give the public at least ten days' notice of the public information meeting. The public information meeting must be held more than ten days prior to the end of the public comment period on the draft site permit. The commission shall extend the comment period if necessary to meet this requirement.
Any person may request in writing that a contested case hearing be held on an application for a site permit for a proposed LWECS project. The contested case hearing request must be filed within the time period established for submitting comments on the draft site permit. The person requesting the public hearing shall include, as part of the request, the issues to be addressed in the hearing and the reasons a hearing is required to resolve those issues.
The commission shall order a contested case hearing if the commission finds that the person requesting the contested case hearing has raised a material issue of fact and that holding a hearing would aid the PUC in making a final determination on the permit application.
For a contested case hearing, the commission shall identify the issues to be resolved and limit the scope and conduct of the hearing according to applicable law, due process, and fundamental fairness. Alternatively, the commission may request the administrative law judge to identify the issues and determine the appropriate scope and conduct of the hearing according to applicable law, due process, and fundamental fairness.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
Upon completion of the procedures and requirements of this chapter, the matter must be brought to the commission for a final decision. If a contested case hearing has been held, the commission shall act according to applicable requirements for action in a contested case proceeding. If no contested case hearing has been held, the commission shall compile the record that has been created and make a decision on the basis of that record.
The commission shall take final action on the application for a site permit for an LWECS within 180 days after acceptance of an application by the commission, unless the applicant agrees to an extension or the commission extends this deadline for cause.
The commission shall not issue a site permit for an LWECS unless the commission determines that the project is compatible with environmental preservation, sustainable development, and the efficient use of resources, and the applicant has complied with this chapter.
The commission may include in a site permit conditions for turbine type and designs, site layout and construction, and operation and maintenance of the LWECS, including the requirement to restore, to the extent possible, the area affected by construction of the LWECS to the natural conditions that existed immediately before construction of the LWECS and other conditions that the commission determines are reasonable to protect the environment, enhance sustainable development, and promote the efficient use of resources.
The term of a site permit for an LWECS is 30 years. The commission may renew the permit for an appropriate period of time upon request of the permit holder.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
Nothing in a site permit for an LWECS shall be construed to convey the right to install a wind turbine in an area within the boundaries of the project for which the permittee does not hold the wind rights.
Nothing in a site permit for an LWECS shall be construed to preclude another person from seeking a site permit to construct an LWECS in an area within the boundaries of the project covered by the permit if the permittee does not hold exclusive wind rights for the areas.
A site permit does not authorize construction of the project until the permittee has obtained a power purchase agreement or some other enforceable mechanism for sale of the power to be generated by the project. If the permittee does not have a power purchase agreement or other enforceable mechanism at the time the permit is issued, the commission shall provide in the permit that the permittee shall advise the commission when it obtains a commitment for purchase of the power. The commission may establish as a condition in the permit a date by which the permittee must obtain a power purchase agreement or other enforceable mechanism or the site permit is null and void.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
If the permittee has not commenced construction of the project within two years after issuance of the site permit, the permittee must advise the commission of the reasons construction has not commenced. In such event, the commission may determine whether the permit should be revoked. No revocation of a permit for failure to commence construction may be undertaken except in accordance with part 7854.1300, subpart 4.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
Once construction of an LWECS is completed, the permittee shall advise the commission of the completion of the project and the commission shall amend the site permit to specifically define the area authorized for the LWECS. The boundary must be no larger than necessary to allow for efficient operation of the LWECS. If any person objects to the amendment of the permit to reflect the actual boundaries of the project, the commission shall bring the matter for decision in accordance with applicable procedural requirements.
The commission may amend a site permit for an LWECS at any time if the commission has good cause to do so.
The commission may revoke a site permit for an LWECS at any time if the commission determines that any of the following has occurred:
the applicant knowingly made a false statement in the application or in accompanying statements or studies required of the applicant, if a true statement would have warranted a change in the commission's findings;
the permitted LWECS endangers human health or the environment and the danger cannot be resolved by modification of the permit or LWECS; or
the permittee has violated other laws that reflect an inability of the permittee to comply with the permit.
The commission may initiate action to consider amendment or revocation of a site permit for an LWECS on its own initiative or upon the request of any person. No site permit may be amended or revoked without first providing notice and affording due process to the permit holder.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
A permittee of a site permit for an LWECS may apply to the PUC for the transfer of its permit. The permittee must provide the name of the existing permittee, the name and description of the person to whom the permit is to be transferred, the reasons for the transfer, a description of the facilities affected, and the requested date of the transfer. The person to whom the permit is to be transferred shall provide the PUC with information required by the PUC to determine whether the new permittee can comply with the conditions of the permit. The permittee shall provide notice of the request to those persons identified by the PUC as persons interested in the matter.
The commission shall approve the transfer if the commission determines that the new permittee will comply with the conditions of the permit. The commission, in approving the transfer of a permit, may impose reasonable additional conditions in the permit as part of the approval. The commission may hold a public meeting to provide the public with an opportunity to comment on the request for the transfer prior to making a decision.
26 SR 1394; L 2005 c 97 art 3 s 19
September 18, 2009
An applicant for a site permit under Minnesota Statutes, section 216F.04, shall pay an application fee to the PUC. The purpose of the application fee is to cover actual costs necessarily and reasonably incurred in processing an application for a site permit, including, but not limited to, staff time, expenses for public notice and meetings, environmental review, administrative overhead, and legal expenses.
Upon receipt of an application for a site permit, the commission shall estimate the costs the PUC expects to incur in processing the application and establish an estimated budget. If the applicant disagrees with the amount of the estimated budget, the applicant may request that the Public Utilities Commission determine the appropriate estimated budget.
Upon determination of the estimated budget, the applicant shall pay at least 50 percent of the estimated budget to the PUC. The commission shall not process a permit application until the first portion of the fee is submitted. The PUC shall deposit all money received from an applicant for permit fees in a special account.
The remaining costs incurred by the PUC must be paid in periodic payments upon receipt of an invoice from the PUC. The PUC shall not make a final decision on a site permit application if any assessed fees are unpaid.
At the end of the permitting process, including any judicial review of the commission's final decision, the PUC shall provide a final accounting to the applicant of the total cost of processing the permit application. The applicant may review all actual costs associated with processing an application and present objections to the commission. The applicant shall make the final payment within 30 days of notification, or the PUC shall refund any excess payments within 30 days of the final accounting.