Within 45 days after acceptance of the application by the commission, the commission shall make a preliminary determination whether a permit may be issued or should be denied. If the preliminary determination is to issue a permit, the commission shall prepare a draft site permit for the project. The draft site permit must identify the person or persons who will be the permittee, describe the proposed LWECS, and include proposed permit conditions.
A draft site permit does not authorize a person to construct an LWECS. The commission may change the draft site permit in any respect before final issuance or may deny the site permit.