In determining whether to issue a permit for a large electric power generating plant or a high voltage transmission line, the commission shall consider the following:
effects on human settlement, including, but not limited to, displacement, noise, aesthetics, cultural values, recreation, and public services;
effects on land-based economies, including, but not limited to, agriculture, forestry, tourism, and mining;
effects on the natural environment, including effects on air and water quality resources and flora and fauna;
application of design options that maximize energy efficiencies, mitigate adverse environmental effects, and could accommodate expansion of transmission or generating capacity;
use or paralleling of existing rights-of-way, survey lines, natural division lines, and agricultural field boundaries;
use of existing transportation, pipeline, and electrical transmission systems or rights-of-way;
costs of constructing, operating, and maintaining the facility which are dependent on design and route;
27 SR 1295; L 2005 c 97 art 3 s 19
This part is repealed effective July 1, 2025. L 2024 c 126 art 7 s 15; L 2024 c 127 art 43 s 15.