A permit from the PUC is not required to construct a power plant of less than 50 megawatts or a transmission line of less than 100 kilovolts. Proposers of such projects must obtain whatever approvals may be required by local, state, or federal units of government with jurisdiction over the project.
27 SR 1295; L 2005 c 97 art 3 s 19
This part is repealed effective July 1, 2025. L 2024 c 126 art 7 s 15; L 2024 c 127 art 43 s 15.