The qualifying facility which negotiates a contract under part 7835.3600 must be entitled to the full avoided capacity costs of the utility. The amount of capacity payments must be determined through consideration of:
the willingness and ability of the qualifying facility to provide firm power during system emergencies;
the willingness and ability of the qualifying facility to allow the utility to dispatch its generated energy;
the willingness and ability of the qualifying facility to provide firm capacity during system peaks;
the smaller capacity increments and the shorter lead times available when capacity is added from qualifying facilities.
9 SR 993
February 28, 2000
Official Publication of the State of Minnesota
Revisor of Statutes