The points assessed for permit application types designated in this subpart shall be multiplied by the dollar per point value as determined in part 7002.0018 to calculate the application fee.
Application Type | Points | |
A. | Administrative amendment or administrative change of name, ownership, or control | 1 |
One point shall be assessed for a request for an administrative amendment or a request for change in name, ownership, or control of a stationary source as addressed in part 7007.1100, subpart 8; 7007.1110, subpart 15; 7007.1142, subpart 5; or 7007.1400. | ||
B. | Registration permit | 2 |
C. | State general permit | 3 |
D. | Part 70 general permit | 4 |
E. | Minor amendment | 4 |
F. | Capped permit | 4 |
G. | Applicability requests | 10 |
These points shall be applied to each request received for determination of the applicability of rules in advance of receipt of a permit application. If multiple requests for reviews are submitted to the Pollution Control Agency over time, each request is subject to the fee. | ||
H. | Moderate amendment | 15 |
I. | Major amendment | 25 |
J. | Individual state permit | 50 |
K. | Individual Part 70 permit | 75 |
The points assessed for activities designated in this subpart shall be multiplied by the dollar per point value as determined in part 7002.0018 to calculate the additional fee.
Activity | Points | |
A. | Modeling review | 15 |
The points for modeling review shall not be assessed for screening modeling or CAPS modeling. | ||
B. | Best available control technology (BACT) review | 15 |
BACT points shall be applied for each prevention of significant deterioration (PSD) pollutant analyzed. | ||
C. | Lowest achievable emission rate (LAER) review | 15 |
LAER points shall be applied for each nonattainment new source review (NSR) pollutant analyzed. | ||
D. | Clean Air Act, section 110(a)(2)(D)(i)(I) review | 10 |
Points shall be applied for a review of any standard or other requirement related to interstate transport of pollutants established under section 110(a)(2)(D)(i)(I). | ||
E. | Part 75 continuous emission monitoring analysis | 10 |
F. | New source performance standard (NSPS) review | 10 |
Points shall be applied for each applicable standard but do not apply to registration, capped, or general permit applications. | ||
G. | National emission standards for hazardous air pollutants (NESHAP) review | 10 |
Points shall be applied for each applicable standard but do not apply to registration, capped, or general permit applications. | ||
H. | Case-by-case maximum achievable control technology (MACT) review | 20 |
Points shall be applied for each applicable source category reviewed. | ||
I. | Netting | 10 |
Points shall be applied for each prevention of significant deterioration (PSD) pollutant for which a netting analysis is performed. | ||
J. | Limit to remain below programmatic regulatory threshold | 10 |
Points shall be applied, if applicable, to each of the following regulatory programs: Part 70, NESHAP, EAW, AERA, NSPS, PSD, and nonattainment NSR. | ||
K. | Plantwide applicability limit (PAL) | 20 |
Points shall be applied for each prevention of significant deterioration (PSD) pollutant for which a plantwide applicability limit is established. | ||
L. | Air emission risk analysis (AERA) review | 15 |
M. | Variance request under part 7000.7000 | 35 |
N. | Confidentiality request under part 7000.1300 | 2 |
O. | Environmental assessment worksheet (EAW) review | |
Points shall be assigned as follows: | ||
Part 4410.4300, subparts 18, item A; and 29 | 15 | |
Part 4410.4300, subparts 8, items A and B; 10, items A to C; 16, items A and D; 17, items A to C and E to G; and 18, items B and C | 35 | |
Part 4410.4300, subparts 4; 5, items A and B; 13; 15; 16, items B and C; and 17, item D | 70 | |
A fee for EAW review shall be charged only if the project falls into a mandatory category specified in part 4410.4300, the agency is the designated responsible governmental unit (RGU), and an air or water permit is required for the project. If a facility requires both an air and water permit, the points for an EAW review shall be charged only once and multiplied by the lower of the dollar per point value for an air or water permit. |
34 SR 1205; 41 SR 763
January 27, 2017