For a task listed in this part, the cost is prima facie unreasonable when it exceeds the amount specified for it in the bid for contractor services or the maximum cost specified for it in this part when the task was started, whichever is less.
Mobilization/demobilization (heavy equipment), including crew and equipment.
Equipment | Maximum cost |
Dozer, loader, backhoe, or excavator, 70-250 hp. (0 to 50 miles one way) | $240 each |
Dozer, loader, backhoe, or excavator, over 250 hp. (0 to 50 miles one way) | $360 each |
Saw-cutting.
Surfacing material | Maximum cost |
Asphalt | $1.67 per linear foot |
Concrete | $4.80 per linear foot |
Soil disposal.
Volume | Maximum cost |
0 to 10 cubic yards | $666 |
11 to 150 cubic yards | $666 or $53 per cubic yard, whichever is greater |
151 to 500 cubic yards | $7,986 or $47 per cubic yard, whichever is greater |
more than 500 cubic yards | $23,293 or $40 per cubic yard, whichever is greater |
Surface removal.
Surfacing material | Maximum cost |
Asphalt | $5.46 per square yard |
Concrete (mesh-reinforced) | $13 per square yard |
Concrete (rod-reinforced) | $17 per square yard |
Surface replacement.
Surfacing material | Maximum cost |
2-inch asphalt (including compacted gravel base) | $2.66 per square foot |
4-inch asphalt (including compacted gravel base) | $5.32 per square foot |
6-inch reinforced concrete (including a minimum of 4-inch compacted gravel base, forms, concrete in place, finish, and cure) | $9 per square foot |
8-inch reinforced concrete (including a minimum of 4-inch compacted gravel base, forms, concrete in place, finish, and cure) | $11 per square foot |
MS s 115C.07
20 SR 227; 28 SR 383; L 2010 c 241 s 4; MS s 115C.07 subd 3 paragraph (f); 20 SR 227; 28 SR 383; L 2010 c 241 s 4; MS s 115C.07 subd 3 paragraph (f)
July 5, 2017
Official Publication of the State of Minnesota
Revisor of Statutes